|
11. |
The Roof Fix the Roofing Iron to the Purlins with appropriate
roofing nails/screws. Fix to the top and bottom
Purlins at every second corrugation and fix to the
intermediate Purlins at every 3rd or 4th
corrugation. Fix through the high side of the
corrugation.
Overhang the roofing approx 65 (2 1/2") past the
Fascia Board or 50 (2") past the back of the gutter.
|
 |
12. |
Ridge
Capping and Barge Flashing Standard Ridge Capping is about 130 (5") each side
of the apex, but can vary and any size can be made
to order. Have the Ridge Flashing in mind when
positioning the top Purlin. Fix to the Purlin at
every second corrugation.
The Barge Flashing goes under the Ridge Capping at
the top. Fix to each purlin (through two
corrugations) and also to the barge board. |
|
13. |
Cladding UnderlayA Cladding Underlay should envelop the exterior
walls prior to the cladding being fixed.
|
|
|
|
14. |
Exterior
Vertical Boards Commence fixing the Boards to the Wall Frames,
beginning from one corner. Cut the Boards long
enough so that they will touch the underside of the
Rafter at the top and run at least 50mm (2") below
the floor.
Nail the Boards to the Noggings with nails
approximately 75mm (3") apart (including the nail
that will be going through the Batten). Leave a gap
between each board.
|
|
15. |
The
Battens Fix the Battens 75x25 (1x3) over each join.
Preferably, the battens should have a groove each
side of the join to stop water being drawn up by
capillary action.
Nail on the center line of the Batten, through the
gap between the Boards and into the Noggings.
Overlap on corners (see picture). |
 |
16. |
Done! Install the Door, install the Window and you're
done! |